ADU Construction Plans: What to Include Before You Build

Somewhere on your lot there's a spot you've already picked out. Maybe it's the gravel pad past the pool, or the side yard the landscaper never finished. You've pictured a casita there, sketched a rough footprint on a napkin, and started browsing kitchenettes and covered patios.

That napkin is where most ADU projects go sideways. The floor plan is the last thing the site decides, not the first. Before a single wall line gets drawn, three numbers control what you can build: how the lot is zoned, how large the existing house is on the assessor's record, and how much room the setbacks and coverage rules actually leave you.

Homeowners routinely pay for a two-bedroom casita design the lot can only support at 900 square feet. Catching that at the start costs nothing. Catching it after the drawings are stamped costs thousands.

Eligibility and ADU Types Before Design

Start with the lot file, not a floor plan. Zoning, the assessor card for the existing house, and the ADU type that card can support decide whether design is even worth opening.

Arizona law requires municipalities with populations over 75,000 to allow at least one attached and one detached ADU as permitted uses on lots where a single-family dwelling is allowed, per the state statute. Cities still write the local tests. A state minimum is not a permit.

Scottsdale permits three types, attached, detached, and restricted-affordable detached units, and limits eligibility to a single-family residential lot that already holds one main single-family dwelling, per the city's accessory dwelling unit code page.

Work the eligibility file in this order:

  1. Confirm zoning and the existing dwelling. Pull the assessor record and verify the main house is documented as a single-family dwelling. An unpermitted conversion, a lot split that never got recorded, or a property carrying two meters from an old guest setup can stall the file before design starts.
  2. Shortlist the types the lot can support. Two candidates is enough. One attached, one detached, both plausible, neither final. The documented area of the existing home is the limit those candidates have to fit. Design inside that verified number. Do not sketch the rooms first and trim them later.
  3. Hold the attached-or-detached decision until the setback survey is done. Attached units follow different rear and side-yard rules than detached ones, so the choice belongs after measurement, not before it.

Scottsdale's local process still requires a development application and review before any ADU permit issues. A lot that fails should fail here, while the only cost is a records search, not a full architectural set.

Eligibility rule: If the assessor record doesn't clearly show one main single-family dwelling, stop and fix the record before anything else.

If part of the motivation is rental income, model the money as carefully as the zoning. This guide to ADU cash flow walks through how owners think about rent, payback, and unit economics before they commit capital.

Action: record the zoning designation and main-dwelling status in a project file, and shortlist two ADU types before anyone walks the lot with a tape measure.

ADU Size Caps for Phoenix and Scottsdale Lots

Say the main house measures 1,200 square feet on the assessor record and you want a two-bedroom casita with a full kitchen. The lot is wide, the setbacks work, and the design you like runs larger than the cap allows. In Phoenix and Scottsdale that plan is dead on arrival, and no amount of finish revision saves it. The ceiling is 75% of the existing home's gross floor area, which puts you at 900 square feet.

This is why the site-yield test runs before the sketch. The cap isn't a guideline a variance can soften. It's arithmetic tied to a document the city already has.

Phoenix applies the cap differently depending on lot size. On lots up to 10,000 square feet, an ADU is limited to the lesser of 1,000 square feet or 75% of the primary dwelling's gross floor area. On larger lots, the cap becomes the lesser of 3,000 square feet, 10% of net lot area, or 75% of the primary dwelling's gross floor area, per the City of Phoenix ADU guidance. Scottsdale keeps it simpler: the first ADU is limited to 1,000 square feet or 75% of the existing main residence's size, whichever is less, and any additional ADU is capped at 500 square feet, according to the city's ADU frequently asked questions.

Case Phoenix cap Scottsdale cap
Lot up to 10,000 sq ft Lesser of 1,000 sq ft or 75% of primary gross floor area First ADU: lesser of 1,000 sq ft or 75% of main residence
Lot over 10,000 sq ft Lesser of 3,000 sq ft, 10% of net lot area, or 75% of primary gross floor area First ADU still limited to the lesser of 1,000 sq ft or 75% of the main residence
1,200 sq ft primary home 900 sq ft 900 sq ft first ADU
2,000 sq ft primary home 1,000 sq ft (lot up to 10,000 sq ft) 1,000 sq ft first ADU
Additional ADU Two ADUs allowed on qualifying single-family detached lots, each tested against the same cap 500 sq ft maximum

Run the test on your own lot

  1. Pull the documented area. Assessor records and permit history, not your own measurements. A finished basement or an enclosed patio may or may not count toward gross floor area, and the reviewer will use the record.
  2. Calculate net lot area. That means gross lot area minus any right-of-way dedication or recorded easement the zoning code excludes.
  3. Apply the cap that fits your lot size. Phoenix first, then the 75% share of the existing home. The smaller number wins.
  4. Subtract what the cap doesn't cover. Parking, lot coverage, required open space, and the utility pad all eat into the practical buildable envelope even when the ADU area fits on paper.

The number that matters: write the maximum permitted ADU area on the project file before a floor plan exists. Every design conversation after that starts from a real ceiling.

Action: confirm the documented gross floor area and net lot area, apply the cap, and only then brief a designer.

Setbacks, Height and Lot Coverage That Set Placement

Setbacks and height decide whether a detached structure fits at all, once you subtract the existing walls, the pool, the easements, and the utility runs already crossing the yard. Those constraints live in the site plan, not the floor plan, and the City of Phoenix ADU guide puts numbers to them.

A blueprint of ADU construction plans sits on a wooden table with a tape measure outdoors.

Control Phoenix rule Design effect
Maximum height 15 ft absent a use permit Second-story suite may need height or use-permit analysis
Detached interior side and rear separation 3 ft minimum in stated circumstances Narrow side yard favors a detached rear casita
Adjacent dedicated alley No setback Alley-side placement frees up yard space
Lot coverage Must comply with zoning limit Calculate coverage before fixing the footprint

Read the table as a set of design decisions rather than a list of numbers. A five-foot side yard on a lot with an existing wall and a pool equipment pad rarely supports anything but a rear casita. A second-story suite over a garage sounds efficient until the height analysis lands, and the use permit timeline gets added to the schedule.

Attached units are a different animal. They follow distinct rear and side-yard rules, and the addition has to be integrated so the finished house reads as one residence rather than a duplex with a shared driveway. That integration affects roof pitch, exterior material transitions, window alignment, and where the mechanical equipment lands.

Practical rule: choose the type after the survey, not before. The setback overlay usually makes the decision for you.

The plan set that comes out of this stage should show property lines, zoning setbacks, height elevations, lot coverage calculations, access, utility connections, drainage, and how the ADU sits relative to the primary residence. A colored floor plan with furniture in it proves nothing to a reviewer.

Action: overlay the proposed footprint on the survey and mark every boundary, easement, and height limit before choosing a layout.

Utilities, Drainage and Access Checks

A detached ADU can pass the setback test and still fail at the service route. The first constraint is the lot and the existing home's documented area. Verify the survey, easements, and recorded improvement locations first, then design the floor plan within those limits. Electrical panel capacity, breaker space, meter locations, gas routing, water pressure, sewer capacity, drainage fall, and construction access all decide where the unit can sit. Treating those items as early design inputs avoids a plan that looks clean on paper but needs utility trenches through a finished yard or a service upgrade after approval.

Start with the route, not the room sizes. If the main panel has little spare capacity, the scope may include a heavier electrical service. If the gas line, water line, or sewer path crosses the only open yard area, the footprint may need to shift. A longer water run can reduce available pressure at the new fixtures. A septic system already serving the main house at capacity may force a different approach, and an expanded system can materially raise construction cost. The local code framework is worth reviewing through the city's accessory dwelling unit code page, but the site plan still has to show the actual connections.

Use this as a field check before the layout is locked:

  • Sewer or septic capacity. Confirm available capacity at the main house. Trigger: the system is already rated to its limit.
  • Water service and pressure. Trace the run from the meter to the proposed fixture group. Trigger: the new path is long and pressure drops at the far end.
  • Electrical service. Check panel capacity, breaker space, and meter locations. Trigger: the existing panel cannot serve the added load.
  • Gas routing. Size the line from the main and locate the path. Trigger: the run cuts across finished hardscape or a constrained side yard.
  • Drainage path. Roof and flatwork runoff must move away from the new footprint without ponding at the main house. Trigger: the only fall line runs toward a neighbor's lot.
  • Grading and entry. The door threshold has to sit above finished grade with slope away. Trigger: the yard falls back toward the proposed pad.
  • Fire access and hose reach. Crews need to reach the far wall. Trigger: a gate, pool, or wall blocks access.
  • Parking and a clear path from the street. Trigger: the only parking spot blocks the alley or main driveway.
  • Easements across the pad. Trigger: a utility easement crosses the only buildable area on that side of the lot.

Action: request utility and sewer information from the provider and draw the route on the site plan before the layout is finalized.

Layout Choices for Casitas and Multigenerational Suites

The first layout decision isn't the kitchen. It's whether you're building one larger unit or two smaller ones. That choice drives circulation, privacy, fire and life-safety coordination, mechanical distribution, and cost, and it runs straight into the area caps covered above: a single larger unit consumes the entire first-ADU allowance, while any additional Scottsdale unit is limited to 500 square feet.

A comparison chart outlining four key considerations for designing one larger ADU versus two smaller ADU units.

Option Best fit Main trade-off Permit point to check
One larger ADU Full suite with its own kitchen and bath Uses most of the area allowance in one unit Area cap applies to the single unit
Two smaller ADUs Guest room plus a separate casita Splits circulation, mechanical and cost Scottsdale: any additional ADU capped at 500 sq ft
Attached addition Suite that reads as part of the main home Must be integrated so it does not read as a duplex Attached rear and side-yard rules differ
Detached casita Privacy and a separate entry Separate utility routes and a longer path Detached setback and height rules apply

Privacy between generations is usually the deciding criterion. Two units give each household its own door, its own thermostat, and its own schedule. One larger unit gives you a better kitchen and a shorter utility run, but the in-laws walk through your hallway to reach the laundry.

Kitchen and bath counts follow the privacy call. Two units means two of everything, which raises the plumbing scope, the appliance package, and the maintenance load. Accessibility routes matter more than most owners expect: a zero-threshold shower, a wider door at the entry, and a path without steps add modest cost early and are expensive to retrofit.

How construction touches daily life deserves a straight answer up front. When the ADU is a detached casita or guest house and the main home isn't being altered, a homeowner can stay in the main home through construction. Attached additions are a different experience, because the tie-in work runs through the house.

That's the argument for the design and build team sitting together from day one of a project, rather than handing drawings between architect and builder. The structural tie-in, the mechanical routing, and the permit strategy get resolved in the same conversation.

Test before you commit: list what the household actually needs, then run two layouts against the area cap and the separation rules. The one that survives both is your project.

For a closer look at how casitas and multigenerational suites come together on an existing estate, see our accessory dwellings work.

Budgeting and Funding the Plan Before Approval

A real budget arrives after the design and architectural phase, once plans and specifications exist, and typically before permitting begins. That timing matters. Numbers built on a schematic sketch are guesses; numbers built on a defined scope with named finishes hold up through construction.

The lines a homeowner should see itemized

Ask for the budget as line items, not a lump sum. The categories that belong on the sheet: design and engineering, permit and review fees, utility upgrades such as new meters or sewer work, site work and drainage, the building itself, finishes and fixtures, and a contingency for conditions the site investigation didn't reveal. A single lump sum hides the two lines most likely to move, which are almost always site work and utility upgrades.

Construction is funded through a draw schedule, with funds released in stages as materials are purchased and construction milestones are completed. Confirm the schedule in writing, and confirm how each milestone is defined. "Rough framing complete" means one thing to a lender and another to a superintendent.

Before you sign: a line-item budget and a draw schedule should both exist before the final drawings are approved.

The financing questions most plans skip

How a lender underwrites an ADU, whether projected rental income counts toward qualifying, how construction financing converts to permanent debt, and what the added structure does to property taxes and insurance. A 2025 City of Austin research memorandum found conventional lending products were inaccessible to a majority of low- and moderate-income households seeking to finance an ADU, and identified permitting and property-tax impacts as top homeowner concerns. If the cash-out route is part of the plan, read up on cash-out refinance risks explained before restructuring existing debt.

Carrying costs apply even when the suite is for family and produces no rent. Appraisal treatment, utility bills, insurance, and maintenance all continue. The final budget sheet should show the draw schedule, the carrying costs, and the expected change in property taxes and insurance, which is also the point where the scope of a luxury renovation and remodel on the main house should be sequenced against the ADU spend.

Action: request a line-item budget and a draw schedule before approving final drawings, and get the tax and insurance questions answered in writing.

Plan Set Contents and Submission Sequence

A colored floor plan is not a permit-ready set. Reviewers read sheets in a specific order, and each one has to be internally consistent with the others. The set should include the following:

  • Site plan: property lines, zoning setbacks, easements, existing walls, pools, and utility routes.
  • Lot-coverage calculations: the number, the method, and how the ADU affects it.
  • Floor plans: ADU and main house, with room labels and square footages.
  • Exterior elevations: showing finished height against the allowed maximum.
  • Building sections: wall assembly, foundation, and roof structure.
  • Roof and drainage plan: gutters, downspouts, and where water goes.
  • Utility connection plan: electrical, gas, water, and sewer routes with meter locations.
  • Access, parking, and fire routes: how people and equipment reach the unit.
  • Relationship diagram: how the ADU sits against the primary residence.

A checklist of required site plan sheet contents for a residential building permit application.

Every sheet depends on work done earlier. The coverage number comes from the size test. The setbacks come from the survey overlay. The utility plan comes from the provider's information. Draw them in isolation and the reviewer finds the contradictions.

The submission order

Arizona law requires municipalities with populations exceeding 75,000 to adopt regulations allowing at least one attached and one detached ADU as permitted uses on lots where a single-family dwelling is allowed, as set out in the state statute. Local process still runs on top of that allowance.

  1. Start with the online pre-application Scottsdale requires, and submit the site facts rather than a finished design.
  2. Prepare the plan set against the pre-application comments, so the first formal review isn't a discovery exercise.
  3. File the formal administrative-review application with the complete set.
  4. Respond to review comments in writing, sheet by sheet, referencing the comment number.

That coordination work, permitting, city and HOA approvals, and construction oversight from start to finish, is what we manage for clients rather than leaving with the owner.

Action: assemble a site file with assessor records, a survey, and the coverage numbers before any sheet gets drawn.

Confirm Site Feasibility With a Luxury-Rated Builder

Feasibility gets confirmed before the layout is finalized, not after. A plan that fails setbacks or utility routes is cheap to change on paper and expensive to change in the field, because the redesign ripples through structure, mechanical, and finish selections that were already priced.

Bring three things to that conversation. The site file you assembled, with assessor records and the coverage math. The survey with setbacks, easements, and existing structures marked. And the sewer and utility information from the provider, including whether a second meter can be set where you want it.

The right builder starts from those documents rather than a floor plan sketch. That sequencing matters most when the ADU is part of a larger remodel, since the casita's placement affects where the main house can grow and vice versa. In a custom design-build process, the lot and the existing home's documented area set the verified limits first, and the floor plan, room configuration, and layout get designed inside them with the team and architectural partners rather than chosen from pre-drawn plans and trimmed afterward. Every project is assigned an experienced construction manager, a dedicated superintendent, and a project coordinator, so feasibility questions land with someone who owns the answer.

Emery Lane Homes holds Arizona contractor licenses ROC 349148 and ROC 364913, builds ADUs, casitas, guest houses, and multigenerational suites across Scottsdale, Paradise Valley, Arcadia, and the Biltmore corridor, and prices ADU work at a starting average of $400 to $600 per square foot depending on finishes and complexity. The company manages permitting, city and HOA approvals, budgeting, and construction oversight from start to finish, which keeps the plan you approved intact through review and into the build.

Request a site feasibility review before committing to a floor plan. Visit Emery Lane Homes to start that review, and let the lot set the limits the design works within.

You may also like

ADU construction plans explained: layout limits, site rules, permits, utilities and design needs for casitas and multigenerational suites....
Explore 10 luxury home renovation ideas for Phoenix-area homes, from chef's kitchens to ADUs and whole-home upgrades built by a luxury-rated contractor....
Construction management vs general contractor: roles, risk, costs and fit for luxury Scottsdale homes and remodels....